Construction sector: Defend against the weather gods!

AON Insurance discusses strategies for construction companies to protect against rain and climate events


 

Source : aon.com.au

 

Weather and construction delays

 

 

The recent heavy rain in Sydney served as a timely reminder that the risks associated with weather are ever-present. Prolonged La Nina conditions along the East Coast of Australia are ensuring weather continues to play a critical role in construction projects.

Back in 2016, rainfall was above average for most of Australia, with the nationally-averaged rainfall 17% higher than normal.  However, it’s not just rainfall that is a key weather pressure for construction.  The Burea of Metreology (BOM) has also suggested Australia is likely to experience significant warming in the next century. Projections for warming by 2100 range from approximately 2.5 °F to over 6 °F (depending on global greenhouse gas emissions throughout the 21st century).

To avoid unforeseen delays in your build programme, Alister Burley, Aon’s Construction Practice Group Leader, provides some tips on how to hedge weather risk.

For construction companies, weather-based pressures are extensive and need careful consideration as they could adversely impact upon company reputation and financial performance. Key weather concerns for the construction sector include:

  • Unseasonable weather – for example extreme heat meaning roads have to be re-laid
  • Major weather event damaging property ie cyclone, fire, flood or landslide
  • Exposure to unbudgeted project costs as workforces are delayed through inability to work in extreme heat or rain

Hedge your weather risk

With the variety of weather-related risks for the sector considered, how can construction companies manage extreme weather events? According to Burley, there are a number of ways to hedge weather risk, which can be implemented on a per project or portfolio basis. The most common means is through Derivatives.

Derivatives

Weather derivatives are financial instruments that can be used by organisations or individuals as part of a risk management strategy to reduce the risk associated with adverse or unexpected weather conditions. Weather derivatives are bespoke solutions for organisations covering a specific weather event (rain, temperature and wind).  A clear advantage of a weather derivative is access to immediate funds post the occurrence of a defined event (as they are considered “parametric” based and do not required proof of indemnity). The actual events are determined using BOM weather gauges, and most weather derivative risk takers have a Standard and Poors minimum rating of “A”.

This option also provides the ability to transfer risk on a specific contract-needs basis and can provide the ability to cap weather exposure. In some instances it can provide a contract pricing advantage and can help in ensuring cash flow protection through claims being immediately settled.

Aon can help – protection against extreme weather events

Aon, in partnership with expert weather analysts, CelsiusPro, specialise in transferring weather risk from our construction clients’ balance sheets. Our construction clients receive access to Aon and CelsiusPro’s exclusive modelling capabilities, whereby we correlate weather patterns to our clients’ specific projects. With access to immediate climate data, insurance structuring and policy settlement, we can create bespoke weather solutions specific to our construction clients’ requirements.

For more information on construction weather risk and protection options, get in touch with Alister Burley.

 

 

 

Article Image

CAN I POUR CONCRETE IN THE RAIN?

We hear much these days about pouring concrete on hot, dry windy day. But what about when it's raining? 

Article Image

THE FIVE WORST THINGS ABOUT WORKING WITH CONCRETE

I wish they had told me

Article Image

SHOULD I POUR CONCRETE TODAY?

Every day concretors and construction managers tear their hair out unsure of whether they should or shouldn't pour concrete due to the weather conditions.

Article Image

GRAINGER'S GARDEN SUPPLIES

Your first choice in the Swan Valley for all your landscaping needs

Article Image

UPCOMING CONCRETE TRAINING COURSES

Don't miss out on our members upcoming training days

Article Image

HAVE A ROAD, RAIL OR CIVIL PROJECT IN NSW?

The HCH group are your solution

Article Image

HOW TO REMOVE PAINT FROM CONCRETE AND OTHER STAINS

Remove oil and grease stains from concrete using TSP and other cleaners.

Article Image

POP CONCRETE SALES AND TRAINING COMING UP

Find out everything here!

Article Image

WANT BORING, OLD CONCRETE PAINTED? MARK WILL TRANSFORM IT

Kryptonite Coatings transform plain concrete into what looks like everything from floor boards, to sandstone and slate

Article Image

POP CONCRETE SUPPLIES AND TRAINING

Always remember ? Your Success is our Goal

 


Tags: AON insurance BOM weather construction delays hot weather insurance rain


This article was written by marketing@concretebroker.com.au all rights reserved. The views and opinions expressed in this article are those of the author(s) and do not necessarily reflect those of concretebroker.com