Lets talk about vibrating concrete
The University of Hong Kong gives us an insight
Source for this article : http://www.cityu.edu.hk
Vibrators
These are mobile items of mechanical plant used to vibrate (shake) air out of fresh concrete.
There are 2 major types of vibrators:
- External vibrators (Form vibrators)
- Internal vibrators (Poker/Immersion vibrators)
All types of vibrators have motors, which can be driven by:
- Compressed air
- Main supply electricity (230 or 400V & 50Hz) motors
- High frequency electricity motors
- Petrol or diesel (liquid fuel)
![]() Concreting to the precast facade and then compact the concrete by Poker Vibrator to force out the air-bubbles trapped inside. |
Internal Vibrator Usage
Internal vibrators are often used inefficiently. They often run wastefully, or at a reduced efficiency, for about 70% of their operating time, this being made up as follows:
out of the concrete and left running | 15% | ||
wrongly positioned in the concrete | 35% | ||
vibrating already compacted concrete | 20% | ||
Total: | 70% |
This means that the poker is doing useful work for only 30% of the time, which is why it is so necessary to plan the compaction in advance, along with the placing method and technique, so that both operations are done as economically and as quickly as possible.
Source: Dublin, Ireland based hire company, we have this High Frequency Electric Concrete Poker for hire. see our website : hirere.ie
20 Rules for Using Internal Vibrators
- Make sure you can see the concrete surface. Lights may be required in thin deep sections.
- Put the head in quickly. When inserting the poker, allow it to penetrate to the bottom of the layer as quickly as possible under its own weight. If done slowly, the top part of the layer will be compacted first, making it more difficult for the entrapped air in the lower part of the layer to escape to the surface.
- Insert the head vertically. This minimises the voids created by inserting the head, and allows air bubbles to rise up unimpeded by a slopping vibrator.
- Do not stir. This only increases the voids.
- Leave the poker in the concrete for about 10 seconds.
- Withdraw the poker slowly. The main thing is to see that the hole made by the poker is closed up; otherwise you will be left with a hole in the finished concrete. If this does happen-and it is often difficult to prevent if the concrete is very stiff-put the poker back in near enough to the hold for the next spell of vibration to close it up. For the final insertion, withdraw the poker even more slowly and wiggle it about to ensure that the hole closes up properly.
- Repeat insertion. Ensure that in plan (as seen on the surface) all areas covered.
- Avoid touching the form face with the poker. Not only will the form face be damaged but a mark will be left on the finished concrete surface. To be on the safe side, keep the vibrator about 75-100 mm from the formwork.
- Avoid touching the reinforcement with the poker. Provided that all the concrete is still fresh, vibrating the reinforcement should not do any harm and could improve the bond. The danger lies in the vibrations in the reinforcement being transmitted into parts of the section where the concrete may have stiffened, in which case the bond may be affected.
- For shallow flat slabs lie the head in the concrete and drag the head slowly through the concrete. Alternately an external vibrator may be able to be used. If say ¹ of the head can be immersed, the vibrator will not be very effective, and compaction will be slow.
- Avoid using the vibrator to make the concrete flow. You may get some areas of segregation and other areas of fines only concrete. The latter may be weak and cause discoloration.
- Avoid sticking the poker into the top of a heap. Although heaps should be avoided in placing they are sometimes unavoidable or caused by mistake. To flatten a heap, insert the poker around the perimeter. Do this carefully to avoid segregation.
- Make sure that the poker extends about 100mm into any previous layer. This will knit the layers together, and any laitance on top of the previous layer will be mixed with the bottom of the new one. The new layer should not yet of course be rigid.
- The maximum depth of the new layer equals vibrator head length minus 100 mm. If the depth of concrete is greater, then the new part will not be fully compacted.
- Put the whole length of the poker into the concrete. This is essential to keep the bearings cool.
- Avoid leaving the poker running when it is not in the concrete. Otherwise there is a risk of bearings overheating.
- Avoid sharp bends in flexible drives. Otherwise the shaft can be broken.
- Remember that, where finish is important, a little bit of extra vibration can reduce the number of blowholes.
- Make sure the drive motor will not vibrate itself off the staging. Do not remove it by pulling the flexible drive.
- Clean it afterwards.
Cover Photo courtesy of Getty Images
Image credits
Creator:Construction Photography/Avalon
Credit:Getty Images
Information extracted from IPTC Photo Metadata
Length of Time Required for Full Compaction
- Initial consolidation is rapid and the level of the concrete drops, but the entrapped air has still to be removed.
- As the concrete is vibrated, air bubbles come to the surface. When the bubbles stop it can be taken as a sign that not much more useful work can be cone on the concrete. The distance of the bubbles from the poker is also a useful guide to its radius of action.
- Sometimes the sound of the poker can be a helpful guide. When the poker is inserted there is usually a dropping off in frequency, and when the pitch (whine) becomes constant the concrete is free of entrapped air.
- The surface appearance also gives an indication of whether or not compaction is complete. A thin film of glistening mortar on the surface is a sign that the concrete is compacted, as is cement paste showing at the junction of the concrete and formwork.
Revibration
On columns and walls where surface finish is of importance, there is sometimes a tendency for blowholes to occur in the top 600 mm of a lift; the reason is that, unlike the lower layers, this top layer does not have the advantage of the weight of additional concrete on top to increase the compaction. It can often help to revibrate the top 500 mm within the first 15 minute after the initial compaction.
In thick sections of slabs and beams, and particularly with mixes are prone to bleeding, there is a danger of plastic cracks appearing within 1-2 hours after compaction. If they are noticed within this time, and provided the concrete is till workable, revibration of the top 75-100 mm can close them up again.
Source for this article : http://www.cityu.edu.hk
You may also like :
![]() |
For only the the best concrete tools |
![]() |
ConstructionIndustrySupplies
Concrete Industry Supplies is your one stop shop for everything in the concrete industry. Thats right! Concrete formwork, concrete tools, steel reinforcing, fabricated steel, prefabricated steel and concrete accessories. They've got it all. Not to mention taking off plans and drawings for house and industrial slabs, what about estimating and scheduling as well, it's all there. If its cut and bent bar, a concrete helicopter, or just a trowel, your'e in the right place at Concrete Industry Supplies. |
![]() |
BrenerTools
Seth is the CEO and Co-Founder of Brener Tools, the makers of the SMAKT Tool. SMAKT is inspired by 25 years of plumbing experience. SMAKT helps you core concrete in half the time, half the cost, half the price, and less than half the weight! After 25 years of core drilling, Brener Tools decided to solve an old industry frustration. So, we drew up plans for SMAKT, a new, faster, lighter, and cleaner method of core drilling. Because SMAKT uses 2 core bits simultaneously, you get consistent depth measurement each time; so, no taking apart the drill to change bits. A conventional 4 inch core, which took 60 minutes in non-composite concrete, switching to a 10-inch-bit, could now be finished in 20 minutes with SMAKT. Seth was the owner of George Breslaw Plumbing, LLC. and is a Master Plumber. |
![]() |
Bushhammer
In abujardar.com you will find the necessary tools to make the different textures of Bush hammering, Sandblast and Scratching, applicable to Concrete, stones, marble, granite, sandstone, artificial stone, prefabricated... We are manufacturers and we can create a tool to connect to your specific machine, ask us to study your case and offer you the best option. |
![]() |
FreetDiamondToolsCoLtd
Jiangxi Freet Diamond Tools Co., Ltd ( Freet Company) is a high-tech Co. Ltd, with standardized management and stock ownership. It is combined with scientific research, production, sale and service. Originated from its former pioneer?Minnan Knife Factory, which was a family generated system in 1994, it has renamed as Quanzhou Freet Diamond Tools with modern stock ownership. In order to seek higher development, a larger production base in Jiangxi Province. With our new big factory set in Jiangxi, the company is now named as Jiangxi Freet Diamond Tools. |
![]() |
SolomonColors
We are an employee-owned company that manufactures an innovative line of products providing solutions to enhance the value of architectural concrete. Solomon Colors? decades of experience, dedication to quality, and desire to keep innovation at the forefront of everything we do has placed us at the top of our industry. We look forward to providing more of the same excellent service and quality you have come to expect as a Solomon Colors customer. |
![]() |
SpraypaveeastGippsland
Spraypave East Gippsland provide decorative concrete expertise in the Gippsland region of Victoria for seeking to transform old and tired concrete surfaces into new revitalised features that are both durable and aesthetically pleasing to the eye. Their staple spray pave comes with extended warranty, that is how much they guarantee their product and workmanship. In addition to spray pave they offer stencil, stamped and patterned concrete, all with a view to revolutionising those boring old concrete surfaces that you are tired of looking at. Spraypave East Gippsland offer polished concrete and grinding services for those who require it as well as their highly sought after blanket cover Flec finish |
![]() |
NyconDiamond
NYCON Diamond & Tool Inc. is a New York based full service Concrete Cutting, Core Drilling, Slab Sawing, Wall Sawing, wire sawing, supplier. Our subsidiaries J1 Core & Core 1 Inc provide cutting and sawing services. As a professional cutting company and supplier, we sell and service a complete line of diamond cutting products, safety equipment and power tools. Our mission is simple: to provide the best products and service to our customers at the lowest prices possible. We take great pride in our company, our commitment to customer service and in the products we sell. Our online store is designed to provide you with a safe and secure environment to browse our product catalog. |
![]() |
WHAT ARE THE BEST SKILSAW TOOLS IN 2018 Protool reviews takes a look at the best skilsaw tools from the World of Concrete 2018 |
![]() |
BEST OF 2017 - WORLD'S MOST AMAZING MACHINES IN OPERATION VOL 180 MODERN CONCRETING An array of power floats laser screeds and concrete finishing tools on display and available at concrete broker |
Tags: compacting concrete concrete tools concrete vibration concreting University of HK vibrating concrete vibrators
This article was written by marketing@concretebroker.com.au all rights reserved. The views and opinions expressed in this article are those of the author(s) and do not necessarily reflect those of concretebroker.com